MED - TVC
| Process |
Multiple Effect with Vapour Thermocompression |
|---|---|
| Country | Indonesia |
| Contract Description | Design / Supply / Deliver FOB / Supervision of erection / Commissioning of two desalination unit |
| Contract Date | 2016 |
| Capacity |
|
Project Description :
The units will produce 1 750 M3/day each of distillate water and 240 M3/day of potable water for the Lontar Extension Coal Fired Steam Power Plant located in Indonesia.
Technical Description :
The scope of Entropie consists in the engineering, fabrication and delivery FOB of two desalination units Multiple Effect Distillation (MED) type fitted with a thermal vapour compressor and four evaporation cells. The scole also includes interconnection to the existing installation.